FK Group


Project Name; Plots C1 & D1, The Lightbox, Media City, Manchester
Date; November 2017 – December 2018
Project Value; £1,150,000.00

Works Completed; Full design and construction for the internal leaf of the external envelope of 2nr 20 storey new build high-rise residential towers in Manchester’s prestigious Media City. Our package of works includes the installation of the light gauge SFS framing, external Knauf Windliner sheathing board to the SFS, installation of Knauf Omnifit insulation to achieve the required U-Value and air guard membrane for the air seal. We also installed all vertical and horizontal vented and non-vented fire cavity barriers behind the finished rain screen cladding. All Windliner boarding and cavity barrier works were carried out from external mast climbers.

Caddick Construction


Project Name; Edge Lane, Liverpool Project
Date; October 2016 – October 2017
Project Value; £710,000.00

Works Completed; This project has been split between 3 phases over 12 months. Our scope of works have included Drylining, MF & Suspended ceilings, Fire, Air and Acoustic Sealing, Structural Fire Protection (Intumescent Painting & Boarding), Joinery, Flooring, Kitchen Installation, Decoration and installation of SFS and Jumbo Stud high bay dividing walls. FAA also carried out post construction fit outs on several of the units for the end users after main contractor hand over.

ADT Workplace


Project Name; Bank of New York – 1 Piccadilly Gardens, Manchester
Project Date; June – November 2017
Project Value; £390,000.00

Works Completed; One of the most challenging contracts to date. Due to the nature of the tight programme FAA worked 24 hour shifts, 7 days a week installing various partition types inclusive of High Security Partitions, MF Ceilings, Feature Bulkheads, Bespoke Timber Ceilings and New Suspended Ceilings. A large part of the works involved was to repair circa 8,000m2 of existing ceiling grid inclusive of cleaning and installation of ceiling tiles. FAA also carried out extensive acoustic works to the head of new and old plaster board / glass partitions and under raised access floors as well as plaster / tape and joint finishes to all new partitions and extensive patching to existing retained partitions, ceilings and ceiling margins that were adapted. The installation of all skirting boards & single / double door sets across all 5 floors finally followed to wrap up our works on here. After this contract FAA have carried out over 10 other projects for ADT Workplace varying in size and complexity throughout the North-West and Yorkshire and still continue to be their go to contractor for ceilings, partitions, joinery and acoustic works.

Chalcroft Construction


Project Name; Porcelanosa, Reading
Project Date; April – November 2017
Project Value; £219,000.00

Works Completed; FAA were appointed by Chalcroft to fit out this high end bathroom / tile showroom in Reading. The schedule of works included SFS Structural High Bay Walls, Jumbo Stud Wall Liners, MF Ceilings inclusive of ceiling Margins, a single 450m2 Metal Pan Suspended Ceiling with Sub Grid and back of house partitions / ceilings inclusive of tape and joint finish. We also carried out the Structural Fire Protection and Firestopping Works.

FK Group


Project Name; BUPA – Salford, Manchester
Project Date; June – October 2017
Project Value; £80,000.00

Works Completed; FAA installed circa 2,000lm of Siderise Slab Edge Cavity Barrier inclusive of Acoustic Matting on this beautiful fully glazed prestigious project on the Salford Quays. This was our maiden project for our new client FK Group, a nationwide full envelope contractor. A rigorous step by step quality plan was devised and executed through out the project enabling full sign off by all parties and certification at the end.

ADT Workplace


Project Name; Hexagon Tower, Manchester
Project Date; September – November 2017
Project Value; £56,000.00

Works Completed; Although a relatively small contract sum this is one of the projects we are most proud of. FAA were appointed by ADT Workplace to install new ceilings and partitions to the public areas of the Hexagon Tower comprising of the main reception, toilets and canteen area. FAA installed Feature Bulkheads, Coffered Ceilings, Curved Bulkheads, SFS Metal Pan Ceilings, Armstrong Suspended Ceilings, Varying Trim Details, Formed Booths with Pocket Ceilings & Drylining Partitions.

Chalcroft Construction


Project Name; TJX, Knottingley
Project Date; February – July 2017
Project Value; £179,000.00

Works Completed; FAA were appointed by Chalcroft as the internal fit out contractor for the office pods in the sprawling new TK Maxx distribution warehouse in Knottingley, West Yorkshire. FAA were tasked with installing the SFS Load Baring Structural Frame of the office pods after producing the initial design. Following on was the Plasterboard Lining and Skim to all Walls, Karndean Vinyl Flooring, Suspended Ceilings, Windows and joinery inclusive of all Doors, Skirting and MDF Facias & Decoration. Carrying around 12 skilled site operatives at its peak, it was a real multi-trade project.

JM Construction


Project Name; Tate House P1 & P2, Leeds
Project Date; November 2015 – December 2016
Project Value; £467,000.00

Works Completed; FAA maiden project for local developer / main contractor JM Construction. Our works were split into 2 phases, on the initial phase we installed Rockwool Beam Clad to Concrete Soffits and Beams to 6 existing beam and pot floors to upgrade the structural fire protection. After the first phase was complete, JM Construction we’re to place the order with us for Phase 2 which comprised of 14nr penthouse apartments on the roof of Phase 1. This time we were appointed to carry out the Passive Fire Protection, Drylining, MF and Suspended Ceilings and Plastering works. Works were completed on time and budget.

Gilbert Ash Construction


Project Name; Muswell Hill, London
Project Date; June 2016 – May 2017
Project Value; £120,000.00

Works Completed; We carried out the full Fire, Air and Acoustic sealing works to this high-end 3 block residential development in North London. This project spanned across a number of months and with the use of our internal recording system and flexibility of our site staff has resulted in further Passive Fire Protection being awarded in London for main contractor Gilbert Ash.

Farrans Construction


Project Name; Rushcliffe Arena, Nottingham
Project Date; May – November 2016
Project Value; £164,000.00

Works Completed; FAA were appointed by Farrans to undertake the structural fire protection using Intumescent Paint and Protective Coatings to the steelwork on this leisure development consisting of an Olympic size Swimming Pool, Hydrotherapy Pool and Various Sports Courts. After the initial structural fire protection were completed we were awarded the Fire, Air and Acoustic sealing packages.